UPDATE: West Way access and crane works

West Way access and crane works: updated dates – 29th June, 30th June and 2nd July: SDC have informed us that they have a number of crane lifts planned in association with finishing works to Block B1 of the site. This will result in closure of the site access road from Westminster Way.

The first lift is due to take place on Wednesday 17th June with a further 3 lifts taking place Monday 29th  June, Tuesday 30th June, and again on Thursday 2nd July. The crane will be sited behind the Chancellors temporary office and each lift will result in closure of the road for the whole day. There will be signage in place to warn of the closures with barriers and banksmen present on lift days. Vehicle access to the Co-Op car park will, as before, be via Elms Parade. Pedestrian access will remain in place along Westminster Way with access to and from the Co-Op direct from West Way or via Elms Parade.